¹ú²úÂ鶹AV

ITS to continue network upgrade in selected academic buildings throughout July

ITS to continue network upgrade in selected academic buildings throughout July

Information Technology Services began an upgrade to ¹ú²úÂ鶹AV's entire network last November and will continue with the upgrade throughout July.

As part of this upgrade, ITS will visit individual academic and administrative buildings on the Starkville campus to install new network equipment.Ìý

Careful consideration has been taken on scheduling building upgrade dates to minimize the impact onÌýacademic classes and administrative work.ÌýÌý
ÌýÌý
Please be aware of the following on the day a building is scheduled to beÌýupgraded as theÌýbuilding will be without network connectivity (wired and wireless) all day.ÌýÌý

  • Phones will be unavailable during the upgrade.Ìý
  • Instructors should be prepared to deliver course material from anotherÌýlocation if network access is required.ÌýÌý
  • ITS-supported lecterns will not be functional during the day of the scheduled upgrade.
  • Academic buildings with classrooms scheduled to be upgraded during the month ofÌýJuly are as follows:Ìý
    • Friday, July 2Ìý
      • Magruder HallÌý
      • Patterson Engineering Building
    • Friday, July 9
      • McComas Hall
    • Friday, July 16
      • Dorman Hall
      • Dorman Hall Greenhouse
    • Friday, July 23
      • Howell Building
      • Landscape Architecture Administration
      • Landscape Architecture Freehand Studio
      • Landscape Architecture Seminar Studio
    • Friday, July 30
      • Industrial Education Building

If there are extenuating circumstances that would exclude one of the above buildings from being updated on the specified date and/or time, please immediately notify the ITS Service Desk at 662-325-0631 orÌýservicedesk@msstate.edu.
ÌýÌý
Thank you for your cooperation and understanding during this critical networkÌýupgrade.ÌýÌýÌý